The scope of works included repairs damaged sections of roads, culverts, and bridges in various locations including infrastructure reinstatement.
Gilbert Siding Rd – full replacement of twin cell 1200 dia SW pipes and headwalls at up to 4.0m below finished surface levels, including reinstatement of collapsed unsealed road.
Cleland Gully Rd – full replacement of existing 1200 SW culvert, including scour protection measures downstream of the outlet. Works completed while managing active creek flows.
Myrtle Gully Rd – Repairs of existing triple cell 900 culvert, and new insitu concrete headwalls
Works were completed while managing active creek flows.